Greater Output/ Performance Achieved
TurbinePROs Field Service experts completed a Major Overhaul Hydro Modernization. Due to deterioration and degradation of the original OEM unit, a run-of-the-river hydro plant sought an alternate solution to ensure optimal condition.
TurbinePROs provided full refurbishment with engineering of a new head cover and manufacturing of new wicket gates. These modifications achieved greater output and enhanced operation post refurbishment compared to the original unit.
The streamlined process and hydro field services included technical direction, project management, field supervision, local and key millwright craft labor with extensive experience servicing hydro power plants.
Hydro
S. Morgan Smith
2.3 MW
Details
New Engineering
TurbinePROs provided full refurbishment with engineering of a new head cover and manufacturing of new wicket gates leading to greater output and enhanced operation post refurbishment compared to the original unit
INFORMATION
More Details Coming Soon!
Information
More Details Coming Soon!
Information
More Details Coming Soon!
Unique Project Challenges
Deterioration
Due to deterioration and degradation of the original OEM unit, a run-of-the-river hydro plant sought an alternate solution to ensure optimal condition
Information
More Details Coming Soon!
Information
More Details Coming Soon!
Information
More Details Coming Soon!